|
Completed Projects -
Cemented Rockfill & Concrete Plants
Newmont Mining Corporation
- Deep Post Mine
Minera Meridian LTDA - Chile
Getchell Gold Corporation
- Turquoise Ridge Mine
Kahama Mining Corporation -
Bulyanhulu Gold Mine
Cominco Limited - Polaris Mine
Homestake Canada Inc. - Eskay
Creek Mine
Sistema Hidraulico - Portal
de Entrada
Sistema Hidraulico - Portal
Salida
Cemented
Rockfill Plant
Newmont Mining Corporation
Deep Post Mine
Carlin, Nevada, USA
 |
 |
SIZE / CAPACITY
150 cubic yards per hour
SERVICES PROVIDED
Conceptual Design
Struct./Mech. Engineering
Design & Supply of Control System
Supply/Fabrication of All Equipment
Supervision of Equipment Installation
Commissioning and Training
SUPPLIED EQUIPMENT
Twin Shaft Mixer
Colloidal Mixer
Two Cement/Flyash Bins
Pneumatic Conveying System
Eight Screw Conveyors
Ribbon Blender
1300 ton Aggregate Storage Hopper
Apron Feeder
Two Belt Conveyors
Backfill Mixer Structure
Control Room with MCC/PLC System
Dust Collection System
Pneumatic Control System
|
This multi-level plant is designed for automated
backfill production at Newmont's Deep Post Mine.
The backfill plant utilizes a twin shaft mixer at
the 4084 level, to mix backfill, discharging directly
into haul trucks.
Aggregate is delivered underground by truck to
a 1300 ton aggregate storage silo before feeding
the mixer. Cement and flyash are pneumatically
conveyed from surface and stored in bins on the
4290 level. Here, a blend is produced for delivery
to the backfill area or an underground shotcrete
plant. Once in the backfill area, blended cement
is conveyed directly to the mixer or alternately,
to the colloidal mixer for slurry batching.
All process are controlled by the operator using
PC control, as the operator interface. Fibre optics
are used to communicate with the five PLCs in
the system.
Redundant features in the backfill plant ensure
reliability. In the event the slurry mixer is
unavailable, water and cement may be metered directly
to the mixer. Should the main backfill mixer be
unavailable, trucks may receive aggregate and
slurry at the upper truck bay, ensuring backfill
production continues.
|
Cemented
Rockfill Plant
Minera Meridian LTDA
El Penon, Chile
SIZE / CAPACITY
70 tons per hour
SERVICES PROVIDED
Conceptual Design
Struct./Mech. Engineering
Design & Supply Of Control System
Supply/Fabrication of all Equipment
Supervision of Equipment Installation
Commissioning and Training
SUPPLIED EQUIPMENT
Two Aggregate Conveyors
Pugmill Backfill Mixer
Backfill Holding Hopper
Backfill Mixer Support Structure
125 Ton Cement Silo
Screw Conveyor
1350 Litre Colloidal Mixer
Slurry Surge Tank
Paristaltic Slurry Pump
Dust Collection System
Control Room/PLC/MCC System
Pneumatic Control System
|
The Material Handling Team designed, manufactured,
and commissioned this automated backfill plant.
It is located in the driest location on earth, the
Atacama dessert in northern Chile.
This plant combines cementitious slurry with
coluvium (aggregate), known as 'chusca'. A Thiessen
Tornado slurry system is utilized to prepare slurry
in multiple batches and store it in a holding
tank. Aggregate is stockpiled above a tunnel conveyor
and is then conveyed to a pugmill via a conveyor
scale.
The process is a hybrid system, using automated
slurry batching combined with a continuous process
at the pugmill where the aggregate and slurry
are mixed before discharging to the backfill holding
hopper and haul-truck. The system is mostly self-cleaning,
using the Tornado's colloidal mixer and slurry
pump to purge all lines, the pugmill and gob hopper.
This project was particularly challenging due
to the complexity of coordinating the continuous
processes to sized truckloads up to 20 tonnes.
Two variable frequency drives (VFDs), a conveyor
scale, and a variable speed/reversing peristaltic
pump were utilized within the system to ensure
consistent, high quality backfill.
The unique feature of this plant is the self
cleaning purge cycle inherent within every batch.
The system self-cleans in this manner and may
continue this way for shifts of any duration.
At the end of a shift, a wash formula, (water
only), be run for a final cleaning.
|
Cemented
Rockfill Plant
Getchell Gold Corporation
Turquoise Ridge Mine
Golconda, Nevada, USA
SIZE / CAPACITY
150 tons per hour
SERVICES PROVIDED
Struct./Mech. Engineering
Design & Supply Of Control System
Supply/Fabrication of all Equipment
Supervision of Equipment Installation
Commissioning and Training
SUPPLIED EQUIPMENT
80 Ton Aggregate Storage Hopper
Two Aggregate Weigh Hoppers
Aggregate Transfer Chute
Four Belt Conveyors
Slump Mixer
Two 125 Ton Cement & Flyash Silos
Two Cement & Flyash Weigh Hoppers
Water Weigh Hopper
Seven Screw Conveyors
Cement Storage Hopper
1000 Litre Colloidal Mixer
Slurry Dispensing Head
Control Room/MCC/PLC System
Pneumatic Control System
Six Dust Collectors
Support Structures For All Equipment
Fully Cladded and Insulated Enclosures
|
The Material Handling Team was the successful bidder
in the design, manufacture and commissioning of
Getchell Gold's Turquoise Ridge backfill system.
The plant is comprised of silos, feeders, weigh-bins,
diverters and mixers at various locations throughout
the mine.
Cement and flyash from surface silos and aggregate
from the surface batch plant are fed through borehole
feed lines to a series of transfer and weighing
stations underground. The material is then mixed
in a 10 cubic yard Besser mixer where it is fed
into haul trucks to be used in their underhand
cut and fill operations.
The plant also includes a Thiessen Tornado 1000
on the surface which feeds cement slurry to the
various underground levels where it is sprayed
over development waste for the production of further
cemented rockfill.
|
Concrete
Batch Plant
Kahama Mining Corporation
Bulyanhulu Gold Mine
Tanzania, Africa
SIZE / CAPACITY
80 cubic meters per hour
SERVICES PROVIDED
Conceptual Design
Struct./Mech. Engineering
Design & Supply Of Control System
Supply/Fabrication of all Equipment
Supervision of Equipment Installation
Commissioning and Training
SUPPLIED EQUIPMENT
Aggregate Infeed Hopper
Aggregate Weigh Hopper
Aggregate Conveyor
Two 40 Ton Cementitious Silos
Drive Through Silo Supports
Screw Conveyor
Cement & Water Weigh Hoppers
Bulkbag and 50 kg bag Unloaders
Pneumatic Charge System
Dust Collection System
Control Room/MCC/PLC System
Pneumatic Control System
|
The Material Handling Team was commissioned by Kilborn
SNC Lavalin to supply a complete concrete batching
plant to be used for surface and underground construction
at Sutton Resources' remotely located Bulyanhulu
minesite in Tanzania, Africa.
In order to meet shipping deadlines, The Material
Handling Team completed all design and fabrication,
including all control PLC and MCC systems, in
six weeks. A subsequent flyash upgrade was also
supplied, which features their innovative bulk
bag unloading system, and commissioning of the
entire plant.
|
Cemented
Rockfill Plant
Cominco Limited
Polaris Mine
Little Cornwallis Island, Nunavit, Canada
SIZE / CAPACITY
190 tons per hour (Screening Plant)
125 tons per hour (Mixing Plant)
SERVICES PROVIDED
Conceptual Design
Struct./Mech. Engineering
Design & Supply Of Control System
Supply/Fabrication of all Equipment
Supervision of Equipment Installation
Commissioning and Training
SUPPLIED EQUIPMENT
2000 Litre Colloidal Mixer
Cement & Water Weigh Hoppers
Calcium Chloride Weigh Hopper
Four Screw Conveyors
Three Cementitious Silos
Dust Collection System
Progressive Cavity Pump
Cement Slurry Spraybars
Truck Dump Hopper
Cement Bag Unloading System
Two Apron Feeders
Two Belt Conveyors
375 Tonne Aggregate Storage Bin
Rotary Hot Water Bath System
75 Tonne Surge Bin
Vibratory Feeder and Screen Deck
Control Room/MCC/PLC System
Pneumatic Control System
Two 10,000 Gallon Water Tanks
Heat Exchanger
|
Located only 100 km from the magnetic north pole,
the Cominco Polaris lead-zinc mine is the most northerly
operating mine in the world. When working north
of the seventy-fifth parallel, the Arctic Ocean
only allows a six week window in mid summer to allow
sea access by freighter. Polar bears, caribou, arctic
fox and musk ox are seen almost daily, within the
boundaries of the mine.
In this project undertaken by The Material Handling
Team, 27 truckloads of equipment had to be dockside
in Montreal within a few months or the project
would be delayed for a year. The Material Handling
Team delivered all equipment as required.
The plan called for 8" minus aggregate,
permanently frozen by Arctic conditions, to be
brought in by haul truck, conveyed and stored
in a 375 ton bin. The rock was then fed by a series
of apron feeders, vibratory feeders, and conveyors
through a pre-heat stage and hot water rotary
bath to a second 75 ton storage bin.
Here, a Thiessen Tornado, employing four Colcrete-Eurodrill
colloidal mills combined a cementitious slurry
with the heated rock. 30 ton haul trucks were
then loaded with cemented rockfill for use in
the underground mine. The heated CRF had to withstand
unbelievable ambient temperatures approaching
-70 degrees C, with wind chill.
A single Modicon PLC system with dual touchscreens
was used to monitor and control the entire plant.
The Material Handling Team also provided site
supervision and startup assistance to Cominco
in prime Arctic conditions, October to April.
|
Cemented
Rockfill Plant
Homestake Canada Inc.
Eskay Creek Mine
Eskay Creek, BC, Canada
SIZE / CAPACITY
50 tons per hour
SERVICES PROVIDED
Conceptual Design
Struct./Mech. Engineering
Design & Supply Of Control System
Supply/Fabrication of all Equipment
Supervision of Equipment Installation
Commissioning and Training
SUPPLIED EQUIPMENT
2 Compartment Aggregate Storage Bin
Aggregate Weigh Hopper
Aggregate Belt Conveyor
Teak Pan Mixer
Cement Silo
Cement Weigh Hopper
Concrete Holding Hopper
Dust Collection System
Water Storage Tank
Control Room with MCC/PLC System
Mixer and Silo Support Structure
Fully Cladded and Insulated Enclosures
Pneumatic Control System
|
Eskay Creek Mine is located in British Columbia,
north of Stewart and is one of Canada's premier
gold mine operations.
The Material Handling Team was commissioned by
Homestake Canada Inc. to design and manufacture
a cemented rockfill plant. This batch plant, located
at the mine's lower portal, mixes aggregate, cement,
and water, yielding a premixed cemented rockfill.
The plant incorporates a 3000 litre Teka pan mixer.
The entire process runs automatically using a
Modicon programmable controller and touchscreen,
which is connected via a communications network
to other PLCs at the mine.
This plant was prefabricated and shipped in modules.
The Material Handling Team's contract included
civil engineering, motor control center, erection
supervision and operator training. This plant
is equally capable of producing high quality concrete
and shotcrete, in addition to cemented rockfill.
|
Concrete Batch Plant
Sistema Hidraulico
Portal de Entrada
Yacambu, Estada Lara, Venezuela
SIZE / CAPACITY
60 cubic meters per hour
SERVICES PROVIDED
Conceptual Design
Struct./Mech. Engineering
Design & Supply Of Control System
Supply/Fabrication of all Equipment
Supervision of Equipment Installation
Commissioning and Training
SUPPLIED EQUIPMENT
Aggregate Loadout Hopper
Three Belt Conveyors
Aggregate 3 Position Flop Chute
Aggregate Storage Bins
Three Cement Silos
Three Screw Conveyors
Cement Weigh Hopper
Water Weigh Hopper
Pan Mixer
Concrete Holding Hopper
Dust Collection System
Pallet Lift System
Equipment Support Structure
Control Room/MCC/PLC System
Pneumatic Control System
|
The Material Handling Team was contracted to design,
supply, and commission a pre-mix concrete batch
plant at the portal of this irrigation tunnel. This
batch plant produces shotcrete and concrete for
tunnel lining. This plant featured a 4 yd³
Voeller pan mixer and is PLC controlled. The plant
was commissioned by Material Handling Team personnel
who also performed operator training on-site.
This project involves a 24 km tunnel in Los Andes
spurs, in western Venezuela. The tunnel is to
supply irrigation water from the Yacambu valley
to the neighboring Quibor valley. The contrast
between the lush jungle environment at Portal
de Entrada and the dry desert climate at the other
end, Portal Salida is remarkable.
|
Concrete
Batch Plant
Sistema Hidraulico
Portal Salida
Quibor, Estada Lara, Venezuela
SIZE / CAPACITY
60 cubic meters per hour
SERVICES PROVIDED
Conceptual Design
Struct./Mech. Engineering
Design & Supply Of Control System
Supply/Fabrication of all Equipment
Supervision of Equipment Installation
Commissioning and Training
SUPPLIED EQUIPMENT
Aggregate Loadout Hopper
Three Belt Conveyors
Aggregate 3 Position Flop Chute
Aggregate Storage Bins
Three Cement Silos
Three Screw Conveyors
Cement Weigh Hopper
Water Weigh Hopper
Pan Mixer
Concrete Holding Hopper
Dust Collection System
Pallet Lift System
Equipment Support Structure
Control Room/MCC/PLC System
Pneumatic Control System
|
This project, as described previously in the Yacambu
project, involves the same 24 km irrigation tunnel,
in Los Andes spurs. As with the plant at Portal
de Entrada, in the Yacambu valley, The Material
Handling Team was contracted to design, supply,
and commission a concrete batch plant at the Portal
Salida featuring a Voeller pan mixer. This plant
is also PLC controlled and included an Motor Control
Center as part of the automated package.
The project itself involves tunneling from the
outlet of the tunnel in the Quibor valley, towards
Yacambu. The tunnel, when completed, will be turned
over to the Environmental and Natural Resources
Ministry of Venezuela.
|
|